Port of Auckland - Infrastructure Upgrade Projects

Project Management (client side), engineering design & construction methodology oversight, layout design, Health and Safety management including Safety in Design of changes to existing infrastructure for the Port of Auckland.

Fergusson Terminal 4-High Transition Programme


Challenge / Objective

The Port initiated a major upgrade to transition the full Fergusson Container Terminal to 4-high stacking, enabling increased yard capacity and operational efficiency. This programme required upgrades to straddle fleets, yard infrastructure, pavements, electrical systems, and operational layouts.


The challenge was delivering a large programme made up of multiple sub-projects within a live 24/7 terminal, with strict constraints around access, safety, equipment availability, and operational continuity.


Our Approach

RAMEK acted as a key delivery partner, leading multiple subprojects within the overall programme and working collaboratively with operations, infrastructure, planning, and maintenance teams.


Our approach included:

  • Development of practical, buildable concepts for each subproject

  • Detailed staging and sequencing plans ensuring uninterrupted terminal operations

  • Close coordination with straddle engineering teams for equipment upgrade impacts

  • Safety-in-Design risk reviews across all infrastructure and equipment interfaces

  • Daily onsite presence to ensure quality, speed, and real time issue resolution

  • Programme wide alignment of design, construction, and operational requirements


Results / Outcomes

  • Successful transition to full 4-high capability across Fergusson Terminal

  • Delivery of multiple sub-projects to high quality and within tight timeframes

  • Increased yard capacity and improved stack performance

  • More resilient, future proof terminal layout supporting long term growth

  • Strong alignment between operational needs and infrastructure delivery


eGate Upgrade Programme (Physical & Digital)


Challenge / Objective

The Port required a full modernisation of its eGate system to improve truck throughput, reliability, and automation capability. This upgrade included both the digital software platform and the physical gate infrastructure: roadway layouts, ducting, cabling, sensors, barriers, lighting, and OCR integrations.


All workstreams had to be managed together, delivered in tight windows, and completed without disrupting live gate operations.


Our Approach

RAMEK served as the overall programme manager, leading both the digital and physical upgrade workstreams from planning through to implementation.


Our approach included:

  • Coordinating digital platform upgrades, testing, and rollout with IT and system vendors

  • Managing all physical works, including civil, electrical, and automation infrastructure

  • Facilitating Safety-in-Design workshops across digital + physical streams

  • Close collaboration with Infrastructure, Operations, Planning, Security, and IT

  • Developing and managing detailed staging plans to protect truck flows

  • Providing on-site engineering support to maintain high-quality delivery

  • Leading operational readiness activities to ensure smooth transition


Results / Outcomes

  • Fully upgraded eGate system across digital and physical infrastructure

  • Faster, more reliable truck processing

  • More resilient, scalable, and future-ready gate system

  • Coordinated, integrated delivery across multiple teams and vendors

  • Zero interruption to live gate operations



Project Gallery

CONTACT US

Reach out with any
questions or inquiries

ADDRESS

Glendhu Rd, North Shore, Auckland

PHONE

+64 211 152 7777

EMAIL

  • LinkedIn

© 2025 Ramek Consulting Ltd
Powered and secured by Wix

bottom of page