Port of Auckland Multicargo & Marine New Office Buildings – Infrastructure & Site Services
Port Marine and Multicargo Facilities Upgrade
Client: Port of Auckland
Sector: Port Infrastructure & Facilities
Role: Site Services Project Manager (Ramy) & Construction Project Engineer (Kevin)
Duration: September 2025 – February 2026
Challenge
To facilitate the installation of new prefabricated office facilities for the Multicargo and Marine teams, the existing Portacom office complex required demolition and replacement. The project involved delivering all supporting infrastructure and site services while maintaining port operations, minimising disruption to staff, and ensuring a safe environment for both pedestrians and vehicles within an active operational port environment.
Ramek's Role
Project management of all enabling works and site services delivery
Technical review and coordination of service design packages
Construction management and contractor coordination
Stakeholder management across operational and infrastructure teams
Programme, cost, and quality management
Early identification and mitigation of construction and service conflicts
Verification of contractor works against design requirements
Coordination of works within a live operational environment
Project Scope
Water supply infrastructure
Stormwater network upgrades
Wastewater infrastructure
Electrical power supply and distribution
Pump station works
Internal roads and pavements
Site lighting upgrades
Traffic management and pedestrian safety improvements
Line marking and vehicle circulation enhancements
Enabling works supporting installation of new prefabricated office facilities
Outcomes
All infrastructure and enabling works delivered on programme and within budget
Successful coordination of construction activities within an operational port environment
Improved workplace facilities for the Multicargo and Marine teams
Enhanced pedestrian and vehicle safety through improved traffic management, lighting, and site layout
Upgraded site services and infrastructure to support long-term operational requirements
Early identification and resolution of design and construction issues, preventing significant downstream impacts to programme, cost, and operations
High-quality delivery with minimal disruption to day-to-day port activities
Project Impact
This project provided the critical infrastructure foundation for Port of Auckland's new Multicargo and Marine office facilities. Ramek's involvement from design coordination through to construction delivery ensured that essential services, roads, lighting, and supporting infrastructure were delivered safely and efficiently within a complex operational environment. The completed works not only enabled the successful relocation of staff into modern facilities but also improved site-wide safety, traffic movement, lighting, and overall functionality for port personnel and visitors.
Client Testimonial
As Head of Property, I had the pleasure of working with Kevin on three projects: the Manukau Heads viewing platforms, the associated fencing works, and Shed 7. I also worked with Ramy alongside Kevin on the new Marine and Multi Cargo buildings delivered by TransBuild, in collaboration with Debbie Leigh and me. Throughout these projects, Kevin and Ramy consistently demonstrated the highest levels of professionalism in their interactions with colleagues and stakeholders, as well as in the quality of their work. Their commitment to excellence and attention to detail resulted in completed facilities that will serve the Port well for many years to come.
Elliot Oliver - Head of Property, Port of Auckland
Project Gallery